Project+/Executing

      KICK OFF MEETING

      • meet with sponsor to review the output
      • a meeting at the beginning of the project or major phase of the project
      • align peoples' understanding of project objectives, procedures, and plans
      • begin the team-building and bonding process.
      ↑Jump back a section

      WEEKLY TASKS

      • check scope
      • check evolution and status deliverables
      • check schedule
      • analyze variances, compare estimates to actuals
      • handle scope changes
      • list, track, try to resolve open issues
      • report project status
      • push for activity close-out and deliverable sign-off
      • decide if it's necessary to kill project
      ↑Jump back a section

      EVM (Earned Value Management)

      EVM (Earned Value Management)

      • a method for integrating scope, schedule and resources
      • used for measuring project performance
      • compares
        • amount of work that was planned (PV)
        • what was actually earned (EV)
        • what was actually spent (AC)
      • determines if cost and schedule performance are as planned.

      EVA (Earned Value Analysis)

      • most commonly used method of performance measurement
      • integrates scope, cost and schedule measures
      • assesses project performance
      • used to identify any divergence from planned outcomes

      EV (Earned Value)

      • EV = PV * % complete (from course prep)
      • formerly BCWP (Budgeted Cost Work Performed)
      • value of work actually completed

      PV (Planned Value)

      • formerly BCWS (Budgeted Cost Work Scheduled)
      • portion of approved cost estimate planned to be spent on activity during given period.
      • physical work scheduled to be performed

      AC (Actual Cost)

      • formerly ACWP (Actual Cost Work Performed)
      • total costs incurred in accomplishing work during given period.
      • occurred to accomplish earned value

      BAC (Budget at Completion)

      • the original total budget allocated to a project.
      • sum of all budgets allocated to a project

      EAC (Estimate at Completion)

      • 3 formulas to calculate EAC
        • EAC = AC + ETC
        • EAC = AC + BAC - EV (variances are atypical)
        • EAC = BAC/CPI (from course prep) (variances are expected to occur again at same rate).
      • value expressed as either dollars or hours
      • represents the projected final costs of work when completed
      • actual costs incurred plus estimated cost of remaining work.

      CPI (Cost Performance Index)

      • CPI=EV/AC
      • ratio of worth to cost
      • measure of cost-efficiency or efficiency of the budget
      • CPI < 1.0 means that the task is over budget

      CV (Cost Variance)

      • CV=EV-AC
      • difference between worth and cost of completed work
      • identifies the area where spending more than budgeted
      • CV < 0 means the task is over budget

      ETC (Estimate to Complete)

      • ETC=BAC-EV
      • expected additional cost needed to complete an activity or project

      SV (Schedule Variance)

      • SV=EV-PV
      • difference between worth and supposed-to-be worth of completed work
      • identify schedule problems
      • measure of schedule efficiency
      • SV < 0 means the task is behind schedule

      SPI (Schedule Performance Index)

      • SPI=EV/PV
      • schedule efficiency ratio of earned value accomplished against the planned value
      • describes what portion of the planned schedule was actually accomplished.
      • SPI < 1.0 means the task is behind schedule

      TCPI (To Complete Performance Index)

      • TCPI=(BAC-EV)/(BAC-AC)
      • ratio of remaining work to remaining budget
      • efficiency that must be achieved to complete remaining work with remaining money
      • TCPI>1 = must increase performance to stay within budget

      CAPS (Control Account Plans)

      • management control unit in which earned value performance measurement takes place
      • formerly called Cost Account Plan
      • EVM CAPs continuously measure project performance by relating 3 independent variables
        • Planned Value
        • Earned Value
        • Actual Costs

      Formulas Summary:

      • CV=EV-AC
      • EAC (Estimate at Completion):
        • EAC = AC + ETC
        • EAC = AC + BAC - EV
        • EAC = BAC/CPI (from course prep)
      • CPI=EV/AC
      • SV=EV-PV
      • SPI=EV/PV
      • TCPI=(BAC-EV)/(BAC-AC)
      • Funds Remaining (BAC or EAC - AC)
      • EV=PV*%complete (from course prep)

      Formula Mnemonics For Basic Formulas (CV,SV,CPI,SPI)

      • "V" in left-most means variance which means subtract
      • "I" in left-most means index which means divide
      • "EV" on left side of equation after "="
      • if cost "AC" is right-most, otherwise "PV"
      • CV=EV-AC
      • SV=EV-PV
      • CPI=EV/AC
      • SPI=EV/PV

      Formula Mnemonics For TCPI

      • TCPI=(BAC-EV)/(BAC-AC)
      • remember both num and denom start with BAC-
      • no PV
      • "I" in left-most means index which means divide
      • "EV" on left side of equation after "="

      - baseline

      • original project plan plus approved changes. Must have to use EVA.
      ↑Jump back a section

      CHANGE CONTROL

      Use The Established Procedures Outlined In The Statement Of Work

      Two Methods Used To Monitor Scope Changes

      • track number of scope changes
      • track dollar value of extra work performed

      Before Approval From The Stakeholders On A Project Scope Modification

      • analyze budget issues and their impact on "common problems"
      • analyze project plan issues and their impact
      • research alternatives for the proposed scope change

      Value Engineering

      • used to evaluate proposed changes

      When Change Occurs, PMS Must

      • identify cause
      • write a status report to document change
      • determine how scope change will impact cost and/or schedule
      • quantify alternative solutions
      • ask users to distinguish between mandatory and optional scope changes
      • determine whether to inform the sponsor
      • gain stakeholder approval

      Objectives Of Change Control Process

      • insure that changes are beneficial
      • know when change has occurred
      • manage changes as they occur

      Preventing Scope Creep

      • scope is well documented and verified in the planning phase
      • team well informed of products and quality procedures
      • develop and follow a requirements management process
      ↑Jump back a section

      LARGE & MULTI-LOCATION PROJECT STRATEGIES

      What May Be Needed

      • communication standards
      • work standards
      • sub-teams
      • focus on milestones
      ↑Jump back a section

      TEAM MANAGEMENT

      Best Practices

      • Shared Challenge
      • Team Identity
      • Balanced Task Assignment
      • Team Support
      • Trust Your Team
      • Earn Respect
      • Be a Team Player
      • Leadership Principles

      Conflict Handling Modes

      • confrontation mode
        • problem solving approach
        • allows parties to work through their differences
        • usually most effective
      • smoothing mode
        • de-emphasize areas of differences
        • emphasize areas of agreement
        • often used when personalities clash
      • forcing mode
        • win-lose approach
        • favored by the autocratic
      • withdrawal mode
        • little gets accomplished

      Task Related Conflict

      • often healthy
      • different approaches to create deliverables discussed
      • better solutions can be achieved

      Emotional Conflicts

      • develop group ground rules to avoid

      Common Causes Of Performance Problems Include

      • team is unfocused or pulling in different directions
      • team is fragmented into special interest or social groups
      ↑Jump back a section

      EXECUTIVE SUPPORT

      Re-enforce by

      • identify source of doubts
      • use interpersonal skills
      • act without creating negative impact
      • use allies and influence
      ↑Jump back a section

      RESOURCE MANAGEMENT

      Issues

      • Contract Labor
      • Outsourcing
      • Material Resources and Suppliers
      • Resource Leveling
      ↑Jump back a section

      PROJECT DELAYS

      Issues Related To Extending Schedule

      • impact on other project goals
      • impact on the rest of the organization
      • impact on the project team
      • impact on the vendors
      ↑Jump back a section

      INTERIM PROJECT REQUIREMENT REVIEWS

      INTERIM PROJECT REQUIREMENT REVIEWS - Process

      • held with the sponsors and users
      • held after the initial requirements are completed
      • held after requested changes to the scope are defined
      • most reviews are face-to-face with affected stakeholders
      • may be held on a periodic basis or as needed
      • Reasons To Hold Non-Periodic Reviews
        • organizational changes
        • misunderstandings arise
        • quality problems
        • budget problems

      INTERIM PROJECT REQUIREMENT REVIEWS - Reasons for

      • provides a quality assurance measure for project performance
      • provides an independent evaluation of project performance/documentation
      • examines the overall health of the project
      • recommends actions to address any significant problems
      • Emphasize Important Project Goals
        • main goals understood?
        • are products being delivered on time?
        • quality okay?
        • budget okay?

      INTERIM PROJECT REQUIREMENT REVIEWS - Acceptable Outcomes

      • approve requirements list as is
      • agree on revisions then resubmit for review and approval
      • agree on revisions then move forward with the planning phase
      ↑Jump back a section

      TURNOVER PHASE

      Transition Work

      • user docs
      • user training
      • help-desk training
      ↑Jump back a section
      Last modified on 1 February 2013, at 20:28